POC Planning Document

POC GOALS: • To test the Maximo upgrade from the current version of Maximo 4.01 to version 6 ensuring full data integrity and accuracy.

• The POC must ensure that the Maximo software is fully operational within the Illovo architecture and environment i.e. the POC must test co-existence with all other Illovo software products and hardware.

• The POC must also ensure that all re-worked existing application interfaces are fully operational on the upgraded version.

• The following new requirements must be met: - Provision of a scheduling tool and full integration with MS project - Fully operational new interfaces as defined in the Functional Specification

• All existing application customisations must be re-applied and must be fully functional

• Reports as defined in the functional specification must be fully functional

• The POC must also result in a standard migration path being documented to ensure a smooth rollout and implementation process.

• To select/Replace the thin client (NCD 200) with new models that meet business requirements (Group replacement)

• To select and install hardware for the Maximo Application/Report server (Maximo & Kronos Sites only)

• The architecture selected must cater for SA and African Maximo hardware requirements.

APPLICATION POC OBJECTIVES

• To migrate all current Maximo transactional data from version 4.01 to the new release version 6 and to document an appropriate migration path.

• Configuration/re-application of all current Maximo customizations as documented in the Functional Specification.

• To determine the migration path for existing Crystal reports on the new Maximo version.

• To configure all required customized reports as documented in the Functional Specification and to ensure that all customized reports are fully operational.

• To ensure that all standard Maximo functionality is fully operational

• To implement a standard scheduling tool (within SA and in Africa) which can be used for the planning and scheduling of maintenance during the off-crop period. The business requirements for the scheduling tool are documented in the Functional Specification.

• To ensure seamless integration with MS project and Maximo

• Provision of adequate management reports as documented in the Functional Specification

• To ensure all current interfaces to Maximo are fully operational

The Scope of this project is to test the amendments of the following Tranquillity Application interfaces to Maximo:

- Inventory interface to Maximo - Issues interface to Maximo - General Ledger (ACK) interface to Maximo - Vendor master interface to Maximo - Purchase Order interface to Maximo - Purchase Order Receipts interface to Maximo - Single Point of Entry interface to Maximo

• To test the following two additional interfaces viz. On line Purchase Requisitions to Maximo and Kronos T&A Interface to Maximo

• To ensure that the current version of Maximo is supported on Illovo architecture and platforms.

• To test the co-existence with all other Illovo applications.

• To ensure that all user hardware meets the Maximo minimum hardware requirements and upgrade end-user hardware where required

• To provide for a smooth migration path in Ubombo and in Malawi

• To provide for a software model that can be implemented at Nakambala and Kilombero.

INFRASTRUCTURE OBJECTIVES:

• Ensure that the hardware selected will cater for future growth, current and new applications. (Based on current information & capacity plan provided by Infowave)

• Specify the correct spec & sizing for the Maximo Web Server for every site based on the site size (ie ML370/ML570, amount of memory and disk) Based on stress and functionality testing.

• Specify the exact configuration / standards of the server : hardware, OS, anti virus, application (IW), (SOP – installation / support )

• Test sms updates of the new Maximo server.

• Assess impact on Network bandwidth, ie Maximo / TS / Linux / GS server (all servers must connect to the network at 1 gig full duplex)

• Current hardware standards will apply which have been proven - HP

• Application functionality test with the new hardware and OS .Test the impact on the server resources .

• Test the entire architecture (Linux server, Terminal server, General server, Print server, Maximo web server) interaction of the servers and printing.

• Conduct P.O.C with the new hardware against existing hardware and all applications

• Test local browsing vs server browsing (memory & OS version upgrades on TS [windows 2003 ent server])

• Impact analysis on different VM plug in ie JRE/JINITIATOR

• Revise technical specifications/architecture for thin clients

• Review/revise client equipment replacement plan

• Decide if the Maximo web server can be shared with Kronos

• Specify the change control process for Maximo web server upgrades from IST / involvement of Bytes

• Specify the support, backup and recovery processes for the server (data, OS, application, anti-virus ) ie Bytes to have admin account , iw to have support account with restrictions to that server and specific services. (How will DR in Africa work?)

• Specify interfaces and key dependant services on other servers (IW)

• Specify DR and dev requirements and environment (hardware & processes) Need a dedicated DR and dev box.

• Specify / Test impact of remoter support to sites (if different)

POC Dependencies:

BTG: • Successful completion of the Windows 2003 upgrade with no major impacts on the Maximo Upgrade project (need to discuss this – may or may not be accurate) • Linux servers need to connect at 1gig • Signed orders for equipment & BTG effort required for POC • Equipment required for POC • Support staff availability • Decision on approach for Windows 2003 upgrade • Acceptance from Illovo that Real life DR scenario's take precedence over testing. Bytes DR testing will only take place for 2 sa and 2 africa sites

IST • Timeous procurement of the Maximo Application server and hardware required for the POC.

• Timeous delivery of the Maximo 6 software to Infowave (15 January 2006)

• Completion of the upgrade initiation tasks by IST as documented below

Installation of MAXIMO 6 on IST development server

Restoration of the Illovo Sezela database

Fully documented Functional and Technical specification signed off by the business representatives.

Preliminary Database upgrade to test the data migration process to determine whether the application utility or scripts will be used to convert the data.

To have documents and completed all screen configurations

To have documented and completed all custom functionality development (Old MAXCUST)

To have documented and completed all required Actuate Report development Completion of internal satisfactory system testing by IST

To have documented all configured business rules.

Completion of the upgrade initiation tasks by Infowave as documented below

Re-work of all existing interfaces must be completed

Analysis, design and build of On line Purchase Requisitions to Maximo and Kronos T&A Interface to Maximo

System testing must be completed.

• No material differences exist between the current installation of Maximo with SA and at Ubombo and in Malawi. IST must have completed a full database comparison between the African and SA sites to ensure that no material differences exist.

• Stress test must confirm sizing of the application Server . If not impact lingth OPoc

POC Environment to be created:

Summary

• Servers : GS (existing 570 dr) , TS (existing 570 dr) , Print (need) , Linux TS (existing 570 dr), New Maximo web server (need a 370) • Clients : Thins (10 latest spec for stress testing?, new?) fats – 4 (functionality) - old and new thins (will there be a once off replacement/ phased in replacements ? – Likewise with monitors what will the replacement approach be) Test co-existence ??? • Network: 1 switch (need 1 48 port * 100 meg alcatel ) • Server monitoring (TS/Maximo/GS) • Network Monitoring – tool (server to server , server to client) • Bytes Staff – Dirk, Praniel, Stephen or Cas • Location: Infowave meeting room

Systems to be tested: Sezela environment to be re-created • Tranquilllity • Intranet • Payroll - Unique • Report writer / viewer –Drake & Discoever • Kronos & Keymaster • Canepro • OPM

POC Approach
Windows 2003 Upgrade to be performed
Maximo POC to be conducted after 2003 POC
Co-existence and impact on all application to be tested after Maximo POC completed

Dates and Detail steps to be discussed

POC Scope of Work:

BTG Effort:

• Procure loan servers for POC - WTS, App Server 42 days 2006/01/15 to 2006/02/27 (Use existing DR servers for WTS new server needed for App server)

• Procure end user hardware for POC 42 days 2006/01/15 to 2006/02/27

• Setup of Development Environment for POC (WTS, GS, Fat and Thin Clients) - architecture and all operating systems (16 hours - no charge)

• Setup of fat and thin clients – new thin client , new 1024 x 768 monitors ( no charge)

• Restore the Sezela environment onto the development server (explain?)

• Hardware setup of "Maximo Server" (2 hours - no charge )

• Installation of OS on "Maximo Server" (6 hours – PR)

• DeskTop and Server OS support for duration of POC (Estimate total 8 hours)

• Support during User Acceptance and Stress Tests. (Estimate total 8 hours.)

• Performance Monitoring of the various servers during the POC (Estimate total 8 hours) • To ensure that all user hardware meets the Maximo minimum hardware requirements and upgrade end-user hardware where required • Document findings and specifications, graph & statistics of stress testing , configurations (SOPs) (PR / SA : 32 hours.)
Estimate Total hours : 62 billable hours @ R425 = R26 350 (will bill actuals hours spet)

Roll-Out ( for 10 sites) • Review site specific requirements for servers (racks. UPS, aircon etc) • Hardware setup of "Maximo Server" 2 hours, No charge • Installation of OS on "Maximo Server" Includes patches, (6 hours per server ) • Deliver Server to IFW for pre-installation of "Maximo" No charge • Couriering of Server to appropriate mill (No cost for SA mill. Extra cost in Africa – need to agree mode of transport) • Installation of server on-site – no charge – done by the on-site engineer. (on-site engineer will need assistance from the business / Infowave to install the server into the rack) • Onsite Tech to be available during the cut-over week and weekend for support as well as to allow IST and IFW consultants access to servers and server rooms etc. (Need to charge for overtime on weekend and evenings. Needs to be discussed. ) • Senior HO staff available in the event on-site staff require assistance. Budget standby (needs to be discussed)

IST and Infowave Application Development:

• InfoWave together with IST will install, upgrade and test Maximo and its components ( Actuate etc).

• IST and Infowave conduct a "User Acceptance Test" to ensure that the functionality of the upgraded Maximo works and that all interfaces are fully operational.

• IST and InfoWave will conduct a "Stress Test" simulating 20 users to ensure server performance is adequate. How will this be achieved fro an end users perspective

• IST to migrate all Sezela Maximo transactional data from version 4.01 to version 6

• IST to prepare a White paper documenting the data migration approach

• IST to provide a signed off Technical specification for all Maximo customization, business rules and customized reports .

• IST to prepare a White Paper for converting existing Crystal reports to the new Maximo version.

• IST to ensure that all standard Maximo functional is fully operational

• IST to provide a Technical specification for the configuration of the scheduling tool (within SA and in Africa).

• IST to test and prove seamless integration with MS project and Maximo

Infowave development The Scope of this project is to test the amendments of the following Tranquillity Application interfaces to Maximo:

- Inventory interface to Maximo - Issues interface to Maximo - General Ledger (ACK) interface to Maximo - Vendor master interface to Maximo - Purchase Order interface to Maximo - Purchase Order Receipts interface to Maximo - Single Point of Entry interface to Maximo

• To test the following two additional interfaces viz. On line Purchase Requisitions to Maximo and Kronos T&A Interface to Maximo

• To provide for a smooth migration path in Ubombo and in Malawi

• To provide for a software model that can be implemented at Nakambala and Kilombero.

BUSINESS RESOURCES: • To ensure that the upgraded version of Maximo is supported on Illovo architecture and platforms.

• To test the co-existence with all other Illovo applications.

Detailed Infowave Technical Tasks

• Installation and Configuration/Tuning of IBM Websphere,ACTUATE and Maximo Application

• Setup Dev Environment - (Maximo Database, Tranquillity Database, Interfaces, Clients)

• Create New Maximo 5 Database

• Create New Maximo 6 Database

• Upgrade from Maximo 4.1.1 to 5.2 - Write and Test Database scripts - As per IST

• Upgrade from Maximo 5.2 to 6 - Using Upgrade Utility. Backup and Restores of Databases Required - As per IST

• Assistance during the POC w.r.t Report Development

• Interfaces – Tech Detail of Effort ??

• Assistance during User Acceptance Testing

• Assistance in Stress Testing

• Database Performance Tuning

• Documentation (White Papers, Server setup, Client setup, Middleware setup)

acceptance criteria

APPLICATION • Successful Maximo upgrade from version 4.01 to version 6 • Accurate take-on and conversion of historical data with no loss of data or data integrity • Fully operational Maximo package with all current customization being successfully re-applied meeting all current Illovo business requirements. • Fully functional scheduling tool with full integration between Maximo and MS project such that the scheduling tool support the planning and scheduling of offcrop maintenance • The developed reports must meet all current Illovo requirements and must all be fully operational. • Fully Operational interfaces between Maximo and Tranquillity • Adequate performance of the server during the stress test\

ARCHITECTURE

• The hardware must function with the constraints of the existing Illovo architecture. • The hardware is compatible with all existing applications and known future applications • The acceptance criteria listed above will be tested during the planned POC to finalise acceptance sign off. • Analysis of different models of thin clients and selecting the appropriate model • Performance of the proposed Application/Report Server. • Proof of concept testing for all applications including the new Maximo release . • Testing via PC’s • Testing existing range of monitors with new thin client model for screen resolution compatibility • POC server testing for smaller Maximo sites Nchalo and Dwangwa

Reviews and approval

The following reviews and approvals of deliverables are required.

|Deliverable |Review |Approval |
|Thin Client Performance |Ravie Govender |Dave Schaller |
|Application/Report Server Performance |Ravie Govender |Dave Schaller |
|Monitor Replacement |Ravie Govender |Dave Schaller |
|Sign-off of Maximo Functionality |Paddy Richards |Barry Cornish |
|Sign-off of Maximo Customisations |Paddy Richards |Barry Cornish |
|Sign-off of Maximo Customised Reports |Paddy Richards |Barry Cornish |
|Sign-off of Maximo Interfaces |Paddy Richards |Barry Cornish |
|Sign-off of Maximo Scheduling Tool |Paddy Richards |Barry Cornish |
|Sign-off of Integration with MS project |Paddy Richards |Barry Cornish |

PROJECT resources

roles

The following roles and applicable to this project

|Role |Person Responsible |Organisation |
|Project Sponsor |Barry Cornish |Illovo Group IT |
|Overall Maximo Project Manager |Angela Oosthuizen |Illovo Group IT |
|Business Representative |Paddy Richards |Illovo Noodsberg |
|Business Representative |Maurice Schmidt |Illovo Sezela |
|African Representatives |Tokyo Dlamini |Illovo Ubombo |
| |? |Illovo Nakambala |
| | |Illovo Malawi (NH & DW) |
|IST Project Manager |Kobie Van Rooy |IST |
|Infowave Technical |Usheer Singh |Infowave |
|Infowave Development |Ashwin Maharaj |Infowave |
|Functional Representative |Bryan Baxter |BTG |
|Technical Representative |Deon/Andre |Infowave/BTG |
|Project Administrator |Michelle Naidoo |IllovoGroup It |

POC project team

The POC Project Team will consist of the following individuals

|Person Responsible |Organisation |
|Ravie Govender |Illovo Group IT |
|Angela Oosthuizen |Illovo Group IT |
|Deon Somers |Infowave |
|Usheer Singh |Infowave |
|Bryan Baxter |Bytes Technology Group |
|Andre du Toit |Bytes Technology Group |
|Steven Arnott |Bytes Technology Group (Thin Technology) |
|Kobie Van Rooy |IST |
|Ashwin Maharaj |Infowave |
|Bryan Baxter |BTG |
|Deon/Andre |Infowave/BTG |
|Michelle Naidoo |IllovoGroup It |

TEST PLAN

GENERIC TEST OF MAXIMO FUNCTIONALITY

1 Functionality

WORK ORDERS:
• Work order tracking

create, view, and modify work orders,

view PM and scheduling information,

see which job plan and safety plan is applied,

view the originating work order for a follow-up work order,

identify the failure hierarchy for the equipment or location.

• Work requests

• Quick reporting

• Work manager



3. Customised Reports MMR#1 LTA Maintenance - Avoidable/unavoidable maintenance by department MMR#2 Work productivity – manpower utilisation by employee within supervisor MMR#3 Location costs summary – material and labour costs per location MMR#4 Planned/unplanned work ratios by supervisor MMR#5 Location repeat work – work orders by foreman MMR#6 Outstanding work orders / planned hours – per supervisor MMR#7 Call outs last season vs this season – by location and by supervisor

DETAILED TEST PLAN : GENERIC MAXIMO FUNCTIONALITY TEST

2 WORK ORDERS:

Work order tracking

• Create Work orders from here as well as from the Quick Reporting, Work Requests, Condition Monitoring, and Preventive Maintenance modules.

• Change status (change status as the work order progresses – waiting for approval, wait for material, initiate, un-approve, approve, complete, close, cancel) • View status history • Schedule work orders (NB) • Group several work orders (either by selecting a parent in a hierarchy or by multi-selecting via a query) and then choose the Schedule screen which has the following tabs: • Project – create or use an existing project, describe it and set dates. • Work Orders – define the method of driving the project, etc. • Crafts & Tools – choose schedule resources for crafts, tools and shifts • Purchasing – define whether waiting for PR or PO milestones must be factored into the scheduling. • Field/Code map – choose which information should be transferred to the scheduler (define layout) • Generate follow-up work (copy this work order to a new work order for follow up) • Apply route (link route to work order) • Toggle summary/detail • Remove work plan • Select safety components (link more components) • Remove safety plan • Move/modify equipment • View follow-up work • View Purchase Order information • View received services • View hierarchy grand totals (costing) • Test the ASICUST business rules

Work requests

Work requests: Enter details of problem and link to a Location or piece of equipment.
Apply a route if necessary. A customized button allows access to another screen where the Location Downtime Work Order and down time information is captured or viewed.

Quick reporting

Create new or modify open work orders or small jobs.
Actual labor and material usage information can be entered

Work manager (NB only)

Specify which labor you want applied to specific work orders at specific times – Dispatch mode, planning mode, centralised despatching, self despatching.

3

4 PREVENTIVE MAINTENANCE

Add scheduling and work order details. Each PM record is linked to equipment, location or a GL account. It can be linked to a job plan if only one needed. Connect to a Route (an equipment hierarchy) if wanted.

Build a hierarchy of PM jobs, which will then generate a hierarchy of Work Orders

View sequence (view a projected long-term job plan sequence based on settings from the Job Plan Sequence tab).

Generate work order (Generate scheduled work orders for your work assets using frequency, hierarchies, etc.)

Create associated PM’s (associate PM’s to a Master PM)

OFF CROP PERIODS

This is a customized screen – created for Illovo, where details of off-crop start and end dates over four years are recorded

5 INVENTORY (Infowave to test)

- Reorder (direct issue and stocked items) - Issue item - Transfer item - View on order quantities - View vendor analysis (prices, quality, performance) - View item availability - Adjust inventory – reconcile balances - Adjust inventory – zero YTD quantities - Adjust inventory – adjust current balances - Adjust inventory – adjust physical count - Adjust inventory – adjust standard cost - Adjust inventory – adjust average cost - Adjust inventory – change capitalized status (GL Accounts) - Add item to storeroom - Add/modify storeroom - Remove items

Issues and transfers

- Select reserved items (show items reserved for work orders) - Issue reserved items to a work order (drag from reserved list) - Select equipment spare parts - Modify reservations (reserve items for a work order) - Select items for return (receive previously issued items back into store) - Move/modify equipment (move equipment from one location to another or from one parent in hierarchy to another)

Asset catalog setup

- Add/modify Classifications (a master list of classifications) - Add/modify Attributes (list of attributes to be used in classifications & asset register) - Add/modify Measure Units (standard units of measurement) - Add/modify Domains (lists of text values or numeric values that are valid when entering a specification)

Item assembly structures

6 EQUIPMENT

- View status history - Drilldown (equipment/location hierarchy) - Reset meter readings - Update average units per day (meters) - Move/modify equipment (within locations) - View equipment move history - Zero equipment costs - Change item number

Operating locations

- change status (decommissioned, operating, planned) - view status history - open drilldown (to link locations to locations) - select system (to link into an existing network)

Failure codes

Condition monitoring

- Generate a work order (If the equipment’s measurements are outside the acceptable limits one can generate a work order)

Routes Generate work order

PURCHASING

Purchase requisitions (Interface Test)

- Assign PR items to a Purchase Order: (Use the actions to either create a purchase order from the unassigned items on the PR, or assign individual lines to a PO.) - Change PR status: (Status is initially set to “wait for approval”. This status can be changed and a history is kept). - View status history: (allow viewing of changes to status) - Move/modify equipment - Add/modify Order Unit values (list of measurement units & conversion factors) - Add/modify Standard Services (list of services eg. freight)

Request for quotation (??)

- change status
- view status history
- define PR to RFQ filter
- copy PR line items to RFQ
- modify multiple quotation lines
- move/modify equipment

Purchase orders

- Change status - View status history - Define PR to PO filter - Copy PR line to PO line - Create PO from PR - Create/View agreements (blanket & pricing agreements) - View vendor analysis for item - View related PR line items - View all PR line items - View Invoice lines - Complete/Approve receipts

Invoices (Not to be tested)

- View status history: (the history of status changes for an invoice). - Add/Modify order units: (Maintain a common table used for converting units from the order unit-of-measure to the issue unit-of-measure). - Add/Modify standard services: (Maintain the common table listing standard services, such as Freight. The data held covers code, description, prorate indicator, GL account code and Tax rate). - Distribute costs (enter a cost once and distribute between line items)

7 PLANS

Safety plans

Safety plan:

Hazards & precautions:

Hazardous materials:

Tag outs:

Safety hazards

Hazards:
Precautions:
Tag outs:

Safety precautions

Lock out / tag out

8 LABOR

Crafts Labor reporting Labor groups

9

10 CALENDARS

- Calculate calendar work hours (calculate the total number of work hours between specified dates) - Summarize working time by craft (view a summary of working hours for a craft) - Go to date - Apply non-working time (specify a non-working period, such as Personal, Sick, Vacation, or Other, to apply to the calendar). - Delete work periods (from the current calendar or from selected calendars). - Define/apply shifts (create shifts to apply to the calendar). - Define/apply holidays (define or modify a list of holidays to apply).

RESOURCES

Tools

CUSTOM APPLICATIONS

Test all current CUSTOM APPLICATIONS and how the customisation has been re-pplied

Master list of custom built and extra applications that have been created.

- SEASONS – Off crop periods - OCHIST – Off crop history - LOCDOWN – Location downtime - RESETPM – Reset PM for Off Crop - LOCX – Additional Location Info - WOX – Report downtime

Reports and other apps

Test all Customised Reports MMR#1 LTA Maintenance - Avoidable/unavoidable maintenance by department MMR#2 Work productivity – manpower utilisation by employee within supervisor MMR#3 Location costs summary – material and labour costs per location MMR#4 Planned/unplanned work ratios by supervisor MMR#5 Location repeat work – work orders by foreman MMR#6 Outstanding work orders / planned hours – per supervisor MMR#7 Call outs last season vs this season – by location and by supervisor

Analyzer Report Writer Failure analysis Inventory analysis Labour analysis Material forecast analysis Vendor analysis Work analysis

SQR Report Writer Employee attendance analysis Availability stats by location Call out report x 2 Restore links Daily maintenance schedule by supervisor Equipment cost rollup report x 4 Delinquent work order report Employee job assignments Daily work order assignment Electronic commerce file APPENDIX A : MAXIMO TEST PLAN

These are the recommended steps to ensure that the data from the Illovo Financials is being inserted into the interface tables.

Issues Interface:
1. Choose a material item.
2. Choose and example Works Order number from Maximo. Validations to be tested
3. Create an issue (301) for this material item and Works Order Number.
4. Run interface program
5. View data on interface table. (MAX_ISU_INTERFACE.inp)
6. View data on Maximo table. (MATUSETRANS.inp)

Inventory Interface:
For the above material item, view information on screen 332.
Check that the item is flagged for copy to Maximo.
Validations to be tested
Run interface B1660
View data on interface table (MAX_ITM_INTERFACE.inp)

Purchase Order Interface:
Create a non-stock PO (127) for the same WO number and authorise the PO (126)
Validations to be tested
Run interface B1664
View data on the interface table (MAX_PO_INTERFACE.inp)

Receipts Interface:
Capture a receipt (145) for the above PO.
Validations to be tested
Run interface B1671
View data on the interface table (MAX_RCV_INTERFACE.inp)

Chart of Accounts Interface:
Run the interface B1662
Validations to be tested
View data for one account on the interface table (MAX_COA_INTERFACE.inp)

- Update database – update GL links on database transactions after changing GL information – three methods from cautious to update all. - Financial periods – define and control accounting periods. - GL Component management – maintain the 8 levels of code which make up a GL account. - Inventory related accounts – a list of locations (courier/labor/storeroom) and any linked GL accounts - Company related accounts – A list of company types linked to 3 types of accounts (RBNI received but not invoiced), AP (accounts payable), AP control account. - Resource control accounts – Internal labor (link work locations to accounts) - Resource control accounts – External labor (link Vendors to accounts) - Resource control accounts – Internal tools (link one account) - Resource control accounts – External tools (link Vendor to accounts) - Resource codes – Labor (categorise labor elements of GL accounts as Outside Yes/No) - Resource codes – Tools (categorise tool elements of GL accounts as Outside Yes/No) - Resource codes – Inventory (link inventory types to account code components)

Companies (Vendor) Interface:
Run the interface B1663
Validations to be tested
View data for one vendor on the interface table (MAX_COM_INTERFACE.inp)

Two new Interfaces (More detail required)
On Line Purchase Requsitions Interface
Kronos –Maximo Interface

Signature security

- View users (list of users for the current group) - Drop users - Drop groups - Add users - Add groups - Re-assign users to groups - Change user password - Set password expiration - Set purchasing limits (set a purchase limit for the current group) - Authorise access to Labor information (restrict the labor/craft codes whose information a user may view) - Authorise access to Storeroom information (restrict the storeroom location codes whose information a user may view) - Authorise access to GL Component information (restrict update on GL components by group)…...

Similar Documents

Premium Essay

Plan

...customer Server Manager: Responsible for the health of server environment of IT infrastructure Configuration Manager: Responsible for the health & management of configuration management system at both server and client side operations. Documentation Manager: Responsible for the standardization, versioning and presentation quality of project documents Database Manager: Responsible for implementation, backup and proper operation of the DBMS. Quality Manager: Responsible for quality standards implementation and test plans. Database Designer: Responsible for designing and implementing the database of the project System Analyzer: Responsible for collecting system requirements and keeping the developers up to date on requirements. Interface Designer: Responsible for designing project interfaces and prototypes. Web Designer: Responsible for design and implementation of presentation web site. Tester: Responsible for following the test plan that is implemented by the quality manager. Developer: Responsible for coding of the project. 6. Project Communication * Project leader has regular meeting with consultant once a month (Project Leadership Discussion in figure). * According to events such as new features project leader and consultant may be hold an extra meeting. * These extra meetings could be face to face or via video conferance. * Over the leadership of discussion meeting, team meetings will be hold one in two weeks. That meeting will......

Words: 2194 - Pages: 9

Free Essay

Plan Approval

...Plan Approval Provide a statement in accordance with the agency’s contingency planning policy to affirm that the ISCP is complete, and has been tested sufficiently. The statement should also affirm that the designated authority is responsible for continued maintenance and testing of the ISCP. This statement should be approved and signed by the system designated authority. Space should be provided for the designated authority to sign, along with any other applicable approving signatures. A sample language is provided below: As the designated authority for {system name}, I hereby certify that the information system contingency plan (ISCP) is complete and that the information contained in this ISCP provides an accurate representation of the application, its hardware, software, and telecommunication components. I further certify that this document identifies the criticality of the system as it relates to the mission of the {Omega Research Inc}, and that the recovery strategies identified will provide the ability to recover the system functionality in the most expedient and cost-beneficial method in keeping with its level of criticality. I further attest that this ISCP for {Information System Contingency Plan} will be tested at least annually. This plan was last tested on {12/3/2011}; the test, training, and exercise (TT&E) material associated with this test can be found {TT&E results appendix or location}. This document will be modified as changes occur and will remain under......

Words: 4591 - Pages: 19

Premium Essay

Plan

...PLAN  In the first step, objective data are collected to identify and address these three issues. Institutional partners are then identified and a multi-disciplinary Quality Concern Team convened to deeply understand the problems and its Root Causes, through systematic Observations that paint a clear picture of the Current Condition. Baseline data are collected to measure whether subsequent improvements actually make a difference. During this phase, it is imperative to develop a business case that describes to all stakeholders (management, staff and patients) why they should care. Once the Current Conditions is examined and understood, the Team articulates what the Target (or ideal) Conditions would be and hypothesizes what will happen when Countermeasures (specific improvements) aimed at achieving that Target Condition are implemented. DO  In the second step, the team takes their understanding of the problem and their vision of the Target Condition and creates an Implementation Plan for carrying out the Countermeasures they believe will achieve the Target Condition. Frontline staff then carries out the Plan and the results are captured. CHECK  In the third step, the Quality Concern Team reviews and analyzes the outcomes of the experiment. Data collected throughout the experiment are compared to the baseline data and to determine if the desired results were achieved. Once the analysis of the data is completed, a report of the outcomes is shared with all......

Words: 511 - Pages: 3

Premium Essay

Risk Management Plan

...------------------------------------------------- Risk Management – Sector I Risk Management Plan Introduction Version 1.2.0 Designed by: Defense Logistics Information Systems Designers: Matthew Gugumuck Michael Mawyer Daryl Giggetts | Overview | * The goal of the Risk Management plan is to design and execute the implementation of various security policies and different counter-measures in the event of any type of risk, threat, and/or vulnerabilities against the organizations daily operations and sensitive information. By combining both hardware devices and software applications will boost the effectiveness of security and preventing unauthorized access and effectively repulsing attacks. | Authority/Ownership | * Any information and sensitive contents contained in this document has been planned and developed by DLA Logistics Information Service and in which is the rightful owner of this document. All materials contained within this document is considered CLASSIFIED and is also copyrighted by DLA Logistics Information Service (DLIS). Any wrongful use of such material and/or reference to this document without the rightful expressed and written consent of the owner(s) may result in criminal prosecution. | Sections contained in DLIS Risk Management Plan | * Risk Management Overview * Planning and Implementation of Risk Management * Key Personnel Roles * Risk Assessment Plan * System Analysis and Characterization ......

Words: 4166 - Pages: 17

Premium Essay

Genrays Communiation Plan

...Communication Plan Template GenRay’s HRIS System Project Communication Plan GenRays 1 November 2013 Document|Author or Originator|Required Date or Frequency|Key Internal/ ExternalStakeholders|Action Required(I,C,A)|Comments| Ongoing Project Status/ Records|Project Team Members|Daily or as Change is made|All Stakeholders|I|Project will be tracked on SharePoint Portal. All task/ milestone updates will be made by team members daily so Management can view overall status at any time. Issues are also tracked here, minor issues will be documented although no approval needed.| Project Report|PM|Monthly|Select Team Leads, Senior Leaders|A|Team members will be present once per month to discuss project in person and answer any specifics that arose from daily project status. Check is progress is meeting Stakeholder expectations. Major issues are identified, discussed, and approved here| Resource Meeting|PM|Bi-Weekly|Project Team, mid-level leaders|C|Team will meet bi-weekly to discuss progress and resource status. This will determine if budget or other resources will need to be changed and request will result from this meeting| Performance Report|Section Leaders|Bi-Weekly|Team Leads|C|Leads will meet immediately following Resource Meeting to discuss performance of employees and the project to identify required changes| Process Meeting|Section POC|As needed|Related Personnel|A|Prior to a major task/ milestone, previously identified personnel will meet to discuss......

Words: 290 - Pages: 2

Premium Essay

Plan to

...Plan for Recruiting and Training Correctional Staff Patricia Saylor Dexter Levin Corrections November 24, 2013 With the increased growth in the level of lawbreakers and the high level of inmates in jails and correctional facilities in proportion to the shortage in correction officers, there has been a growing need for recruitment of more professional correctional staff to help in curbing this issue. With this in mind, the position that the State Director of Corrections will hold shall entail a number of responsibilities. One among the greatest ones will be coming up with a plan for recruiting and training correctional officers. Correctional officers are part of the criminal justice system where their work deals with overseeing arrested individuals who are awaiting trial or overseeing inmates. Planned recruitment and training will ensure continuity and professionalism in the practice leading to enhanced public safety, respect for all humans and upholding of their rights and more sound correctional practices in communities enhancing the community’s faith in the law. Effective management of policies will result in saving of finances, since trained officers will know how to deal with situations better hence lowering the level of injuries incurred at work. Good management policies will result in improvement of correctional officers’ performance, since better terms of work will be adapted thus increasing the officers’ morale to work. Good management policies will lead......

Words: 704 - Pages: 3

Premium Essay

Plan

...Plan The purpose of the paper is to provide an overview of marketing plans. I will do this first by providing the definition of marketing plans. I will discuss how a marketing plan helped make a product or service successful. I will also discuss how decisions in a marketing plan led to failure; I will analyze what was the difference in two examples. Next, I will provide a movie that was considered a box office failure. I will apply what I have learned about the concept of marketing plans, and what could have gone wrong in the studio’s plan with regard to forecasting demand for the project. Let’s begin with sharing my understanding of marketing plans in the roles that it plays. Marketing plans are tools used by managers to guide the process of marketing. Marketing contain strategies and consider many environmental aspects that work together to affect the success of the product or service being marketed. Marketing plan details a company’s marketing effort. It may be laid out for an individual product or for the entire company and all its products. Marketing plans helps establish, coordinate and direct marketing efforts. Marketing plans has different keys to success. Successful marketing requires companies to have capabilities such as understanding customers and competitors, creating customer value and keeping customers. An example of how a marketing plan helped make a product or service successful would be Kellogg’s Special K cereal. The market plan for this company was......

Words: 330 - Pages: 2

Premium Essay

Plan

...of this product / service, then to draft a marketing plan. The objective of the marketing plan is to architect a strategy to build brands (thus creating profits), and to provide a vehicle for others in the firm to have input into that strategy. You should complete the following tasks in your marketing plan. Task 1 First, you need to analyze your company’s current situation and conduct completed marketing audits. 1) Examine organizational and environmental auditing techniques that affect your marketing planning. (1.3) 2) Carry out organizational and environmental audits for your company based on your analysis of the previous question. (1.4) Task 2 Then, you should formulate marketing mix strategies for the product / service and finalize a marketing plan which will be reported to the board of your company. 1) Examine techniques for developing new products. (3.3) 2) Justify recommendations for pricing, distributing and communicating a product or service. (3.4) 3) Explain how factors affecting the effective implementation of the marketing plan have been taken into account. (3.5) 4) Write a marketing plan for the product or service you chose and prepare for a short presentation of your plan. (3.1) Suggestions 1) You can cooperate with each other to collect information for the same product. However, the marketing plan must be written individually. 2) Follow the standard format of a marketing plan. You can download a template from the course......

Words: 393 - Pages: 2

Premium Essay

The Plan

...The Plan Obama’s ceremonial swearing-in at the U.S. Capitol was filled with traditional pomp and pageantry. Obama swore in January 21, 2013 for the public. He delivered a speech that previewed the priorities that he intends to pursue for his second-term (Tribune Newspaper, n.d.). His priorities include things like: gun rights, budget plans, and jobs for America. Obama is calling to give a fair shot to the middle class (Dorning, 2013). The Affordable Care Act is also in his plan for the next four years. Obama propose the “The Budget Plan”. Jobs for America, the middle class, and affordable care were discussed in this plan. Amy Goodman stated, “President Obama has unveiled a budget plan seeking to trim the federal deficit by cutting or eliminating over 200 federal programs, many dedicated to social services and education.” The Budget was a $3.7 trillion proposal that would cut funding in half for the IHEAP (Income Home Energy Assistance Program). This program subsidizes heating costs for low-income Americans. President Obama called for a freeze on annual domestic spending over the next few years. The Budget Plan also calls for cutting $300 million from community development block grants. Obama’s plan includes two modest tax hikes for banks and oil companies. However, the Budget does not only include those things. The Budget implements the tight discretionary spending caps that Obama signed into law in the Budget Control Act of 2011. Barack also wanted to limit an expansion......

Words: 1128 - Pages: 5

Premium Essay

Plan

...costs to replace the defective widgets have increased. This comes as a surprise to management because in previous years returns were less than one percent. After compiling the data from the consumer surveys, we decided to give you, the employee, a survey on your job performance, management, and work environment. We also asked you to give any suggestions on how we can improve. The results of the employee surveys have been calculated. Per the survey, many of you stated that you were getting bored with your daily tasks. After weeks of deliberation, we’ve put together an organization motivational plan that will be given to each team member. The motivational plans main focus is team work, which we believe that through teamwork, we can achieve more and continue to provide to our consumers, a state of the art WooWoo. Over the next six weeks, we are expecting the motivational plan to improve in the following areas: high job satisfaction, low turnover, high productivity, and high-quality work. As you continue reading, you will notice the new policies we have put into place for each of the areas listed above. Job Satisfaction & Low Turnover “Job satisfaction is an employee's thoughts and emotions towards their job and how they evaluate their job. This can be a judgment of their job overall, or of specific judgments such as pay, promotions, work tasks, co-workers and supervisors. It is important for organizations to care about their employees' job satisfaction. It......

Words: 1482 - Pages: 6

Premium Essay

Plan

...Contingency Plan An Update IAATO Vessel Emergency Contingency Plan 2006-2007 IAATO Operational Document Information Paper submitted by The International Association of Antarctica Tour Operators Introduction The following IAATO Vessel Emergency Contingency Plan was agreed to originally at IAATO’s 14th Annual General Meeting, May 2003. It was tabled as ATCM XXVI IP069 and has been in place for all subsequent seasons. At IAATO’s 17th Annual General Meeting, April 2006, the plan was reviewed first by IAATO’s Marine Committee and then presented to all ship operators for discussion and adoption. It was agreed by the membership that the plan was effective and only required additional supplemental text. The plan retains the flexibility to be amended should international shipping regulations be changed or operators find more efficient and practical ways to work. The plan is outlined below, and an IAATO Emergency Contingency Plan Flow Chart, is shown in Appendix A. This paper was originally prepared by Captain Leif Skog and reviewed and or updated each year since 2003. Captain Skog has been working in Antarctica for 27 years and is the Vice President of Marine Operations for IAATO member, Lindblad Expeditions. Background All IAATO vessels operating in Antarctica are required to operate under the ISM Code and consequently they must have a well-established Safety Management System (SMS) in place in addition to the IAATO emergency contingency plans......

Words: 2896 - Pages: 12

Premium Essay

Physical Security Plan

...Perimeter Protection As the Security Manager of Palm Beach Marina Cove (PBMC), I was informed that there will be an expansion to the existing condominium. PBMC II will be built next to PBMC on the east side of the property near the seawall. ABC construction will be the lead company to erect the PBMC II. A construction site has a high probability of internal and external threats. With the ongoing construction, we must put in place a perimeter protection plan. The perimeter protection plan must include best practices in perimeter protection for a construction site that integrates with the contiguous existing building, properly safeguard the perimeter of both sites during construction, my recommendations, and a budget for all recommendations. The protection plan will come with a price but we need to ensure the safety of all the residents of PBMC, but also take into considerations of ABC constructions equipment and materials. With undertaking of this huge project, we must look at the best practices for the construction site that integrates with the contiguous existing building. The first step in this process will ensure that the individuals that are working on the construction site will have a complete background check. The background check will be conducted by ABC Construction. If the employee is suitable to work on the site, he will be issued a badge with his or her picture on the card. If the individual is not suitable for the work site, then he...

Words: 1710 - Pages: 7

Premium Essay

Plan a

...Plan A After high school there are numerous things i want to do and accomplish in my life. My admirations are not much different than the average person , but it will still take a lot of hard work to get where i want to be. After I graduate this May I pan on taking summer classes at Columbus state, while working so I can save/ earn money for college. I am committed to play soccer at the university of charleston next August. My plan as of now is to go to UC to study to be a neonatal nurse practitioner. As a senior, I took four classes at Marion Tech this year and earned 12 credit hours. This summer I plan on taking 6 prerequisites at Columbus state, so once I get to Charleston, I get into the nursing program as a freshman. I was born a month early. When I came out of my mothers stomach I weighed 3 lbs 5 ounces, I was took straight to intensive care, where they were not sure if i was going to make it.. barely breathing. If it wasnt for the neonatal nurses and doctors, I most likely would not be here today. I just feel the need to give back and help save newborn babies lives and take care of them. Neonatal nursing allows you to make a difference in the lives of infants and their families which is my goal. Many neonatal nurses continue to hear from families and infants they have cared for throughout their lives. Neonatal nurses are the voice for the smallest and sickest of patients that have no voice. Ive been told multiple times that the neonatal nursing field is a very...

Words: 637 - Pages: 3

Free Essay

Plan

...The Marketing Plan BY GEORGE SAMIR SAAD Introduction: My department is "AlSalam Nephrology department", in which I am the senior doctor and the responsible for patients and the subordinates –doctors, nurses and workers-. This department one of the most famous oldest unit in Egypt, in which renal transplantation done successfully and legally. The unit has: * 8 renal dialysis machines, * 2 outpatient clinics, * 20 inpatient beds, * 3 professors, * 1 senior doctor, * 5 doctors, * 3 head nurses, * 5 nurses, * 4 assistances, * 2 workers. Situation analysis: Current service: - AlSalam nephrology department, responsible for many services, like: * Renal transplantation, * Follow up renal-transplanted patients, * Renal dialysis for chronic renal failure patients, * Outpatient clinic for kidney diseases; and * Teaching and practicing place for new doctors who care with nephrology. - The unit in AlSalam hospital, which present in ElMohandseen area in Giza, Egypt, which is a famous, commercial, crowded, rich area. - The hospital accredited with ISO 9001 in 2004. -Background information -Date of opening the unit: 1983 -Average No. of outpatient/Day: 60 patients - No. renal failure patients/Day: 20 patients -Costs /outpatient: 40 LE -Revenue /out patient: 120 LE -Net profit /outpatient: - 80 LE, which is good. -Costs / renal failure patients: 200 LE -Revenue / renal failure patients:......

Words: 4619 - Pages: 19

Premium Essay

Plan

...BUSINESS PLAN LIFE LIVE 17 Qing HUA EAST ROAD HAIDIAN, BEIJING CHINA GROUP CHEN SI RUI SHEN SHUANG SUN RONG BIN ZHANG JIA WEI [20.06.2015] Background Along with the social reform, people's consumption ideas gradually change, to a coffee shop to drink coffee is no longer like a few years ago to be far away, like quiet people, will choose to the coffee shop at the weekend through a lazy afternoon, listening to the Italian tunes of rich emotional appeal feel relaxed. College students are also looking for a quiet and comfortable study environment, a 24 hours of leisure, then become indispensable. With the change of the consumer mind, small endowment the coffee industry increasingly rise, in the country has quite a few hidden in set the theme of city shop. These coffee shop consumption is not high, suitable for mass consumption society, general entrepreneurs investing psychology all want to make a lot of money, the fastest way to make money is to make the rich money, instead, in the consumer groups, the audience most is the populace, the biggest consumer spending and civilian class, how to do ordinary and small into many is a very exquisite management strategic problem. Based on this kind of trend, more and more people seek to this shop to enjoy a comfortable environment. For......

Words: 2993 - Pages: 12